Project
KickStart - Product Development Plan Template The
following project was created using a template from Project KickStart
Free Trial. The free trial can be downloaded at http://projectkickstart.com/downloads/download_free_trial.cfm. Please
call with any questions: 510.644.0694.
|
|
# |
Task Name |
Days |
Start |
Finish |
Assignments |
Notes |
|
1 |
Conceptualization |
9 |
3/15/07 |
3/27/07 |
|
|
|
2 |
Brainstorming |
1 |
3/15/07 |
3/15/07 |
President, Project Manager, Sr. Chemist, Mechanical Engineer, Sr. MEMS Designer, MEMS Technician, Marketing Coordinator, Production Laison |
|
|
3 |
Concepts |
5 |
3/21/07 |
3/27/07 |
Mechanical Engineer, Project Manager, Sr. MEMS Designer |
|
|
4 |
Confirm Existing Product Compatibility |
1 |
3/16/07 |
3/16/07 |
Sr. Product Manager |
|
|
5 |
Engineering Phase |
47 |
3/27/07 |
5/30/07 |
|
|
|
6 |
Designing |
11 |
3/27/07 |
4/10/07 |
Mechanical Engineer, Sr. MEMS Designer |
|
|
7 |
Benchtop Tests |
14 |
4/4/07 |
4/23/07 |
Mechanical Engineer, Sr. MEMS Designer, MEMS Technician |
|
|
8 |
Select Prototype Designs |
1 |
4/23/07 |
4/23/07 |
Project Manager, Sr. Chemist, Mechanical Engineer, Sr. MEMS Designer |
|
|
9 |
Prototype |
21 |
4/24/07 |
5/22/07 |
MEMS Technician, Mechanical Engineer |
|
|
10 |
Test Prototype |
13 |
5/14/07 |
5/30/07 |
MEMS Technician, Sr. Chemist, Mechanical Engineer |
|
|
11 |
Pre-Production |
41 |
5/31/07 |
7/26/07 |
|
|
|
12 |
Select Production Design |
1 |
5/31/07 |
5/31/07 |
Production Laison, Sr. MEMS Designer, Mechanical Engineer, Project Manager, Sr. Chemist |
|
|
13 |
Pilot Production |
40 |
6/1/07 |
7/26/07 |
MEMS Technician, Production Laison |
|
|
14 |
Product Testing |
56 |
7/25/07 |
10/10/07 |
|
|
|
15 |
Alpha Tests |
14 |
7/25/07 |
8/13/07 |
MEMS Technician, Sr. MEMS Designer, Sr. Chemist, Mechanical Engineer |
|
|
16 |
Beta Test |
36 |
8/13/07 |
10/1/07 |
Marketing Coordinator, Project Manager |
|
|
17 |
Focus Group Tests |
14 |
9/21/07 |
10/10/07 |
Marketing Coordinator, Project Manager |
|
|
18 |
Production |
23 |
10/11/07 |
11/12/07 |
|
|
|
19 |
Outsourcing Quotes |
10 |
10/11/07 |
10/24/07 |
Production Laison |
|
|
20 |
Approvals |
1 |
11/12/07 |
11/12/07 |
President, Project Manager |
|
|
21 |
Long Lead Ordering |
1 |
10/19/07 |
10/19/07 |
Production Laison |
|
|
22 |
Second Source R&D |
1 |
10/19/07 |
10/19/07 |
Production Laison, Mechanical Engineer |
|
|
23 |
Release |
31 |
11/14/07 |
12/26/07 |
|
|
|
24 |
Product Announcements |
1 |
11/14/07 |
11/14/07 |
Marketing Coordinator |
|
|
25 |
Release to Outsourced Production |
30 |
11/15/07 |
12/26/07 |
Production Laison, Project Manager |
|
|
26 |
Market Release |
1 |
12/24/07 |
12/24/07 |
President, Project Manager, Marketing Coordinator |
|
|
27 |
Trade Show Prep & Coordination |
1 |
11/23/07 |
11/23/07 |
Marketing Coordinator |
|